EV Charging Station Business: Build the Model Before You Buy Chargers

Business case · site host and CPO guide

EV Charging Station Business: Build the Model Before You Buy Chargers

Freeze demand, revenue, cost, responsibility and evidence before hardware turns an assumption into fixed capital.

Technical review: MarvinInternational · destination-specificHG Power DC portfolio: 40–480 kW
Five ledgersDemand · revenue · cost · responsibility · evidence
Three denominatorsPort-time · energy · commercial utilization
Six capital gatesHypothesis to measured scale
24 RFQ inputsMake business and technical quotes comparable

An EV charging station business can be viable, but charger power does not determine profitability. The business case must reconcile contractable charging demand, the local electricity tariff, ownership and financing, site and equipment costs, payment and software fees, operating responsibility, reliability and measured utilization. Build those inputs into downside, base and upside scenarios before choosing Level 2, DC fast charging or a mixed site.

Scope: This is an international planning guide for prospective charge point operators, site hosts, investors and commercial project developers. It is not legal, tax, investment or local engineering advice. Prices, incentives, electricity resale, payment, metrology, accessibility and permitting rules must be checked for the destination.

The EV charging station business decision in 60 seconds

Do not begin with “How many kilowatts should I buy?” Begin with five questions:

Decide first Evidence you need Stop if…
Who will charge? Vehicle population, trip purpose, arrival windows, energy need and repeat behavior Demand is only “EV adoption is growing”
Why this site? Route fit, dwell time, competing supply, visibility, access and power availability Traffic cannot be translated into plausible charging sessions
Who owns the business? Land, connection, EVSE, software, payment, maintenance, data and customer-support owners Every supplier assumes another party owns recovery
What creates contribution? Destination-specific price, tariff, transaction costs, operating costs and separately evidenced indirect value The base case depends on an incentive or retail uplift that is not secured
What unlocks the next capital stage? Written gate criteria and measured pilot/operating data Expansion is triggered by calendar date instead of evidence

If any answer is missing, the next purchase should usually be information—not more charging capacity.

Choose the business you are actually building

“Charging station owner” and “charging station operator” are not always the same entity. The US Department of Energy distinguishes host-owned and third-party-owned arrangements, while the World Bank describes separate charge point operator (CPO) and site-host roles in the wider e-mobility ecosystem. Ownership changes control, risk and revenue; it is not a paperwork detail. DOE ownership guidance and the World Bank ecosystem report provide useful role frameworks.

Model Site host provides Operator/investor provides Host control Main business-case risk
Host-owned, host-operated Land, connection, capital and operating team Specialist suppliers and contractors High Host carries capex, tariff, utilization and recovery risk
Host-owned, managed operation Land, connection and capital CSMS, payment, monitoring, support and/or maintenance Medium to high Contract gaps between hardware, network and field service
Third-party owner-operator / lease Land or parking rights; sometimes make-ready Capital, equipment and operation Low Lease terms, site access, upgrade rights and limited price/data control
Charging-as-a-Service / managed subscription Site and recurring payment; scope varies Financed equipment and managed service Medium Long-term service economics, exit terms and asset/network portability
Concession, joint venture or revenue share Negotiated land, power, capital or demand contribution Negotiated funding and operation Shared Ambiguous risk allocation and revenue-definition disputes

The label is less important than the contract. For each asset and workflow, state who owns it, who pays, who controls it, who receives data, who responds to failure and who can replace a vendor.

Decision model 01 · Five-Ledger Business Case

One missing ledger can invalidate the investment

01Demandusers · job · dwell · kWh · repeatability

02Revenuepayer · unit · price · collection · timing

03Costdevelopment · capex · opex · failure · finance

04Responsibilityasset · software · payment · support · recovery

05Evidenceprecheck · pilot · acceptance · operations · scale
ADVANCE only when all five ledgers reconcile in the downside and base cases

The Five-Ledger Business Case

A bankable operating case is not a single spreadsheet tab. It is five ledgers that must agree:

  1. Demand ledger: sellable charging need by user, vehicle, time and energy.
  2. Revenue ledger: money or documented strategic value created by that service.
  3. Cost ledger: complete development, capital, operating, failure and financing burden.
  4. Responsibility ledger: an owner for every physical and digital service path.
  5. Evidence ledger: proof that assumptions are true before more capital is committed.

If demand and revenue agree but responsibility is blank, faults can remain unresolved. If revenue and cost agree only because an incentive is assumed, the project is not ready. If the hardware plan is complete but the evidence ledger has no pilot or acceptance data, scale is being purchased before the model has been tested.

Build the demand ledger from charging jobs, not traffic counts

Traffic is an opportunity pool, not charging demand. A useful demand record explains why a driver or fleet will use this site instead of charging at home, at a depot, at a destination, elsewhere on the route or not at all.

Segment the charging job

For every target segment, record:

  • vehicle classes and inlet/connector requirements;
  • origin, destination and route purpose;
  • expected arrival windows and day-of-week pattern;
  • dwell-time distribution, not only an average;
  • energy deficit on arrival and energy needed before departure;
  • maximum vehicle charge acceptance across the relevant state-of-charge and temperature range;
  • repeatability: contracted fleet, employee pool, tenant base, corridor traffic or opportunistic public demand;
  • competing charging supply and likely opening dates;
  • access restrictions, queue tolerance and price sensitivity;
  • seasonality, event peaks and growth cases.

The IEA reports that ultra-fast charging deployment is increasing, but only a subset of current vehicle models can use the highest charging power. That is a reminder that nameplate power is not automatically saleable throughput. Vehicle acceptance, dwell time and site demand still constrain delivered energy. IEA Global EV Outlook 2026 charging analysis.

Separate contractable demand from forecast demand

Use three confidence bands:

Demand class Examples Base-case treatment
Contractable Fleet schedule, tenant commitment, service agreement, known employee roster May enter the base case with the contract's limits and attrition risk
Observable Measured arrivals, existing nearby sessions, survey matched to vehicle ownership, pilot data Enter with a conservative conversion range and documented sample period
Aspirational Regional EV growth, planned development, marketing reach, future network effects Upside case only until converted into site-specific evidence

Do not add the same user twice. A fleet driver who also appears in area traffic data is one charging job, not two revenue streams.

Never use “utilization” without its denominator

The word looks precise but can describe different ratios.

1. Port-time utilization

charging minutes ÷ available port minutes

This is useful for queueing and asset occupancy. Define whether fault time, blocked bays, maintenance and reservation periods remain in the denominator.

2. Energy utilization

delivered kWh ÷ theoretical kWh at continuous rated output

This ratio is usually much lower than port-time utilization when vehicles taper, request less than the charger's rating or remain connected without taking full power.

3. Commercial utilization

actual contribution-producing activity ÷ activity required by the business case

This is not a universal industry metric. It is the project's own bridge between measured sessions/energy and its break-even or return requirement.

The Transportation Energy Institute publishes empirical charger-performance benchmarks for a defined sample and period. Such reports are context, not a forecast for a new site. Before using an external utilization number, record its denominator, equipment class, geography, sample, operating period and treatment of faults and blocked time. TEI 2025 Q4 benchmark report.

Build the revenue ledger without counting hope as cash

An EV charging station business can create direct and indirect value, but each line needs a payer, unit, timing rule and evidence source.

Direct charging-service revenue

Depending on local law and the service model, revenue may include:

  • energy-based price per kWh;
  • time-based or session fees;
  • occupancy or idle fees;
  • subscriptions or membership plans;
  • contracted fleet service or reserved-capacity fees;
  • parking bundled with charging;
  • roaming or partner-channel transactions;
  • site lease or fixed host payment;
  • revenue share under a defined settlement formula.

Do not assume every structure is permitted. For example, the EU Alternative Fuels Infrastructure Regulation sets specific transparency and ad hoc price presentation rules for publicly accessible charging, including per-kWh pricing treatment for certain higher-power points. It is an EU example, not a global rule. Consolidated Regulation (EU) 2023/1804.

For each revenue line, freeze:

payer × charging unit × price × billable quantity × collection rate × settlement timing

A price on the screen is not collected revenue. The model must include taxes, payment acquiring, roaming/partner fees, refunds, discounts, bad debt and settlement delay where applicable.

Indirect host value

Retail spend, customer acquisition, employee retention, parking value, brand value or tenant service can matter. They belong in the model only when they are separately measurable.

Use a test such as:

incremental gross contribution from verified charging visits − promotion and operating costs

Do not insert total store sales during charging sessions. Some visitors would have purchased anyway, and charging is not automatically the cause.

Base, protected upside and speculative upside

Scenario layer Include Exclude
Base Contracted/observed demand, current approved tariff, committed costs Unawarded grants, uncontracted fleets, unmeasured retail uplift
Protected upside Demand or revenue supported by a signed option, expansion clause or verified pilot trend General EV-market growth alone
Speculative upside Clearly labelled future networks, ancillary services or property effects Any value needed to keep the base case solvent

If the base case fails without speculative upside, the project has not yet proven its commercial premise.

Build the complete cost ledger

The charger quotation is one line in the cost model. The commercial charging-station cost guide explains why equipment price and installed project cost are different. For business modelling, organize costs by behavior and owner.

Development and pre-construction

  • demand, traffic and site studies;
  • legal entity, licenses, tax and electricity-resale advice;
  • utility application, capacity study and interconnection design;
  • engineering, surveys, permits and accessibility review;
  • land option, lease negotiation and easements;
  • lender, insurance and procurement costs;
  • software/payment architecture and data-protection review.

Capital expenditure

  • utility/service and transformer or switchgear work;
  • trenching, conduit, cabling, panels, protection and metering;
  • charging cabinets, dispensers, connectors and mounting;
  • civil work, drainage, foundations, canopies, lighting, signage and bollards;
  • communications, payment terminal and network equipment;
  • delivery, installation, commissioning, training, spares and as-built documents;
  • accessibility and parking modifications;
  • expansion reserves that are actually included in the design.

Fixed operating expenditure

  • site lease or minimum host payment;
  • software/network subscriptions;
  • connectivity and back-office systems;
  • insurance, licenses, accounting and administration;
  • preventive maintenance and inspection;
  • customer support and field-service readiness;
  • financing, debt service and asset-management costs.

Variable operating expenditure

  • metered electricity energy charges;
  • demand/capacity charges and time-of-use exposure;
  • payment, roaming and revenue-share fees;
  • maintenance parts and field visits that scale with use;
  • refunds, promotions, cleaning and consumables;
  • losses between the utility meter and delivered/billed energy where relevant to the model.

Failure and recovery costs

A failed session creates more than lost kWh sales. It can produce support contacts, payment reversals, technician dispatch, replacement parts, penalties, stranded demand and reputational damage. The DOE identifies electricity, maintenance, networking, pricing, access and utilization data as ongoing operational considerations and stresses that maintenance responsibility should be established. DOE operation and maintenance guidance.

Treat fault recovery as a designed operating process, not a contingency footnote.

Build a scenario model without fake precision

A transparent model can be simple. A precise-looking model with hidden assumptions is dangerous.

Minimum operating equations

For each user segment and time band:

annual delivered energy = sessions per operating day × delivered kWh per session × operating days

Then:

gross charging revenue = billable energy/session/time quantities × applicable prices

net operating revenue = gross revenue − taxes collected for authorities − payment/roaming/revenue-share deductions − refunds

electricity cost = energy charges + demand/capacity charges + fixed utility charges + other tariff components

operating contribution = net operating revenue − electricity cost − variable operating cost − fixed operating cost

project cash flow = operating contribution − taxes − financing cash flows − capital expenditure ± working-capital changes

The exact accounting and tax treatment belongs to qualified local professionals. The point is to keep energy, demand, fees, opex, capex and financing visible rather than collapsing them into “cost per kWh.”

The National Laboratory of the Rockies' EVI-FAST tool similarly treats charger characteristics, usage, electricity price and demand charges as separate financial inputs and supports risk analysis. EVI-X / EVI-FAST.

Run sensitivities on the variables that can break the project

Variable Downside question Evidence needed before base-case use
Sessions What if conversion is slower or demand shifts by season? Observed/pilot data or contract
Energy per session What if users need smaller top-ups? Vehicle and trip data
Vehicle power acceptance What if installed kW cannot be sold to the vehicle mix? Vehicle/inlet envelope
Electricity tariff What if simultaneous charging creates a higher demand charge? Utility interval model and tariff
Availability/session success What if ports are present but not billable? Defined metric, monitoring and recovery SLA
Price What if competition or regulation constrains the tariff? Local competitor and legal review
Capex/timeline What if make-ready or transformer delivery expands scope? Utility/engineering quote and schedule
Opex What if field service, networking or payment fees are higher? Named contracts and rate cards
Financing What if interest, draw timing or covenant requirements change? Lender terms
Incentive Does the project still work if award or timing changes? Award letter and eligibility review

Show a range for each variable and identify which management action changes it. A sensitivity table that does not change a decision is decoration.

Choose Level 2, DC fast or mixed after defining the service

This business article should not duplicate the equipment guides. Use the service job to choose the next technical analysis.

Service pattern Likely starting architecture Business implication Detailed owner
Long, predictable dwell; many parked vehicles Managed Level 2 Lower power per port, more parking-policy and turnover management Commercial Level 2 guide
Short dwell; route or emergency top-up DC fast Higher grid and demand-charge exposure; availability and queueing become critical DC station design guide
Mixed employees, visitors, fleet or public demand AC/DC mix Separate customer, pricing and priority logic; do not average unlike jobs Commercial buyer's guide
Destination lacks a reliable fixed connection or mission is mobile Movable or battery-integrated alternatives Replenishment and dispatch economics replace part of the fixed-site model Mobile charging guide
PV/storage proposed Site energy architecture Model solar coincidence, battery power/energy and grid role separately Solar charging guide

Do not specify “fastest available.” Specify the least-cost service architecture that can deliver the required energy within the required dwell window, with acceptable queue and reliability risk.

Freeze the responsibility ledger

The charging business crosses physical and digital boundaries. A simple responsibility matrix should appear in the commercial contract, technical specification and operating plan.

Interface Accountable owner Required evidence Failure question
Land, access and bay enforcement Named host/operator Site rights, hours, signage and enforcement policy Who removes blocked vehicles?
Utility capacity and tariff Named contracting entity Approved connection, tariff and interval-data access Who responds to demand-charge surprises?
EVSE and power equipment Named asset owner Configuration, warranty, spares and maintenance scope Who authorizes repair or replacement?
CSMS/network Named operator/provider Data fields, availability, export and migration plan Can the station operate if the vendor changes?
Payment/roaming Named merchant and providers Price presentation, settlement, refunds and reconciliation Who owns a failed or disputed transaction?
Customer support Named first-line and escalation teams Hours, channels, scripts, handoff and response targets Who helps an unfamiliar driver now?
Field service Named maintainer Coverage, response, parts, access and closure proof What closes the incident?
Pricing and promotions Named commercial owner Approval rule, tax treatment and change log Who can change price and when?
Data/privacy/cybersecurity Named controller/processors Permissions, retention, incident and exit plan Who reports and contains an incident?
Expansion decision Named investment committee Gate metrics and signed decision record What evidence releases the next capital stage?

The Joint Office's reliability work emphasizes that charging experience depends on location, design, user interfaces, O&M, payment and the wider ecosystem. That is why uptime should not be the only commercial operating metric. Joint Office reliable-charging webinar.

Decision model 02 · Evidence Ladder

Release capital in stages—not on optimism

1HypothesisWho charges, why here?Stop: “EV adoption” only
2PrecheckSite · grid · tariff · rightsStop: connection breaks model
3Demand proofContract · observation · pilotStop: traffic ≠ sessions
4Model freezeOwnership · price · cost · recoveryStop: base needs speculation
5AcceptanceFAT · readiness · SAT · handoverStop: service path unproven
6Measured scaleEnergy · success · queue · contributionAdvance: written gate passed

Use an Evidence Ladder to stage capital

Gate 1 — Market hypothesis

Define the user, charging job, destination and competing alternatives. Stop if the idea is only “there are more EVs.”

Gate 2 — Site and tariff precheck

Obtain site rights, access constraints, preliminary utility capacity, tariff components and a plausible layout. Stop if the connection or tariff can invalidate the service model.

Gate 3 — Contractable demand

Convert users into evidence: fleet schedules, tenant/employee counts, observed sessions, signed interest with quantities or a defensible sample. Stop if traffic cannot become charging need.

Gate 4 — Business Model Freeze

Approve ownership, revenue units, capex/opex owners, downside/base/upside assumptions and failure recovery. Stop if the base case needs speculative revenue.

Gate 5 — Initial phase and acceptance

Install only the justified phase. Complete factory acceptance, site readiness, site acceptance, payment/authentication tests, monitoring, support training and handover. Stop if opening evidence cannot prove the service path.

Gate 6 — Measured scale decision

Review session success, delivered energy, utilization definitions, queue, fault/recovery time, tariff exposure, contribution and customer demand by segment. Expand only when the evidence meets the written gate.

Staging does not mean undersizing the civil and electrical plan blindly. It means separating low-regret future provisions from charger capacity that the current demand ledger cannot yet support.

Project-killer diagnostic

Symptom Likely root cause Verify Mitigation before expansion
Busy-looking site, weak billable energy Parking activity mistaken for charging demand Sessions, unique users, delivered kWh and dwell by segment Reframe target users, access and pricing; do not add ports first
High charging minutes, low energy Tapering, low vehicle acceptance, blocked/idle connection Power trace and state-of-charge pattern where available Match power to vehicles; apply lawful turnover policy
Gross margin collapses in peak months Demand/capacity charge or time-band exposure Utility interval bill against sessions Scheduling, allocation, tariff review or storage study—not automatic battery purchase
Ports online but users cannot pay/start Payment, roaming, authentication or UI failure End-to-end unfamiliar-driver test Assign recovery owner and acceptance test cases
Same fault repeats No closure evidence or spare/service path Incident history, root cause and repair proof Contract parts, escalation and verified closure
Host and CPO dispute settlement Revenue definition or meter boundary unclear Contract, transaction log, meter and payout reconciliation Freeze gross/net definitions and audit rights
Expansion case depends on a grant Incentive substituted for operations Base case with incentive removed/delayed Stage or redesign until operating model survives
Quote comparisons are impossible Vendors priced different boundaries Line-by-line scope and exclusions Issue one Business Model Freeze Pack and technical RFQ

International rules are business-model inputs

Before freezing revenue or cost, responsible local parties must check:

  • whether electricity can be resold and by which unit;
  • price display, ad hoc payment, receipts, refunds and consumer rules;
  • metering and calibration obligations;
  • electrical, building, parking, fire, accessibility and signage requirements;
  • connector and vehicle-market requirements;
  • data, cybersecurity and payment-card obligations;
  • permits, utility agreements and land-use rights;
  • taxes, depreciation, customs, financing and incentive eligibility;
  • required availability, reporting or open-data obligations for funded/public sites.

A rule copied from another country is not a placeholder. It can change payment hardware, software scope, transaction fees, site layout, reporting and the financial model.

Where HG Power fits—and where it does not

HG Power's approved commercial DC portfolio spans 40–480 kW. That range can support different commercial charging architectures, but it does not select a profitable business model. Final input, output envelope, connector, cable, power allocation, payment, networking, protection, environmental and conformity requirements depend on the quoted configuration and destination.

The reviewed CCS1 manual family documents named 120/180/240/360/480 kW models. Those manual figures must not be extended to 40/60 kW products or another regional configuration. Use the product range, specifications and certifications as starting points, then request the exact quoted evidence package.

HG Power can review project inputs against hardware/configuration and documentation boundaries. Destination engineering, permits, utility approval, installation, legal compliance, tariffs and the investor's financial return remain with the responsible project parties.

What supplied project photographs can—and cannot—prove

Multiple charging positions in a supplied commercial-property underground parking project

Supplied commercial-property project photograph showing repeated charging positions and parking context. It supports discussion of bay count, circulation and operating policy; it does not prove charger rating, public access, utilization, revenue, uptime or customer results.
Repeated charging equipment and marked bays in a supplied commercial-property project

Supplied commercial-property project photograph documenting repeated charger placement, marked bays and upstream electrical context. It does not establish public access, exact rating, utilization, revenue, uptime or commissioning performance.

When should you not build the charging station yet?

Pause before procurement when any of these remain true:

  • no user segment has a repeatable or contractable charging need;
  • the business case uses traffic or regional EV registrations as sessions without a conversion model;
  • the utility tariff, service capacity or connection timeline is unknown;
  • charging price or payment structure has not passed local legal review;
  • land/site rights expire before the model's downside investment horizon;
  • no party owns customer support, maintenance, refunds or incident closure;
  • the base case needs unawarded incentives, unmeasured retail uplift or future ancillary markets;
  • available operating cash cannot cover the downside ramp and recovery costs;
  • the chosen vehicles cannot use the power that the revenue model assumes;
  • vendors are quoting different site, software, payment and service boundaries.

“Not yet” is a valid investment decision. It protects capital until evidence improves.

The 24-input Business Model Freeze Pack

Send the same controlled input pack to every technical and commercial bidder.

Market and demand

  1. Destination country and exact site type.
  2. Target users and charging job.
  3. Vehicle list, inlet/connectors and charge-acceptance limits.
  4. Arrival windows, dwell distribution and seasonality.
  5. Energy needed per session and departure requirement.
  6. Contracted, observed and aspirational demand separated.

Site and electricity

  1. Land/site-rights term and access hours.
  2. Parking layout, circulation, accessibility and expansion boundary.
  3. Available electrical service and preliminary one-line diagram.
  4. Complete utility tariff, including energy, demand/capacity and fixed components.
  5. Utility application/upgrade scope and timeline.
  6. Environmental, civil and communications conditions.

Commercial model

  1. Ownership model and financing assumptions.
  2. Proposed charging units and prices, with legal/tax review owner.
  3. Payment, roaming, settlement, refund and bad-debt assumptions.
  4. Host lease/revenue-share terms and meter boundary.
  5. Base, protected-upside and speculative-upside definitions.
  6. Downside operating-cash and capital contingency rules.

Operations and evidence

  1. EVSE, CSMS, payment, support and maintenance owners.
  2. Required monitoring fields and utilization definitions.
  3. Availability/session-success metrics and exclusions.
  4. FAT, site-readiness, SAT and handover evidence.
  5. Spare parts, field-service, escalation and closure requirements.
  6. Pilot and expansion gates, decision owner and review date.

With these inputs, suppliers can quote a comparable boundary. Without them, one vendor may price equipment only while another includes payment, commissioning or service—creating a false comparison.

Frequently asked questions

Is an EV charging station business profitable?

It can be, but there is no universal answer. Profitability depends on contractable demand, delivered energy, pricing permission, electricity tariff and demand charges, capital and financing, payment/network fees, maintenance, reliability, site costs and ownership. Build downside, base and upside cases from project-specific evidence.

How does an EV charging station business make money?

Possible direct streams include energy, session/time/idle fees where lawful, subscriptions, fleet contracts, parking bundles, leases and revenue shares. Indirect host value may exist, but retail or property uplift should be separately measured and should not rescue an otherwise unsupported base case.

What is the most important profitability input?

There is no single input. Utilization is important, but its definition must be explicit and it interacts with price, tariff, vehicle acceptance, availability, capex and fixed costs. A sensitivity model should reveal which variable can actually break the project.

How much does it cost to start an EV charging station business?

The answer requires site and destination inputs. Include development, utility/make-ready, civil and electrical works, equipment, communications, payment, commissioning, software, maintenance, support, land, insurance, financing and working capital. A charger quotation alone is not a startup budget.

Should a new business choose Level 2 or DC fast charging?

Choose from the service job. Long dwell and many parked vehicles may support managed Level 2. Short dwell or route/fleet top-up may require DC fast charging. A mixed site needs separate demand, pricing and priority logic rather than one average utilization assumption.

Should the site host own the chargers?

Ownership offers control over price, data and asset decisions but also transfers capital, tariff, maintenance and operating risk. Third-party models reduce some responsibilities but can limit control and upside. Compare rights, costs, data, exit and recovery obligations line by line.

Can incentives make a weak site viable?

They can change capital economics, but an unawarded or temporary incentive should not substitute for operating demand. Run the base case without it, model award and timing risk separately, and confirm current destination eligibility before commitment.

What should I send a charger manufacturer for a useful quote?

Send the 24-input freeze pack: destination, users, vehicles, demand, dwell/energy, site rights/layout, electrical service and tariff, ownership/pricing, payment/network, environmental conditions, operating responsibilities, acceptance evidence and expansion gates.

About this guide

This guide was prepared for international commercial charging buyers using current primary sources and HG Power's approved product and project evidence boundaries. Technical review attribution: Marvin. No professional title or qualification is implied.

Sources

Configuration reviewTurn the 24-input freeze pack into a comparable technical scope.Contact HG Power →

Turn your model into a quote-ready technical scope

Before requesting equipment prices, complete the 24-input Business Model Freeze Pack. Then contact HG Power with the destination, vehicle and demand data, site electrical information, intended ownership/payment model, environmental conditions and required documentation. HG Power can review configuration and documentation boundaries; the project parties retain responsibility for local engineering, approval, installation, tariffs, operations and financial results.